Contract variation progresses Nimmo Pedestrian Bridge construction

Alpine Shire Council has approved a variation to the Nimmo Pedestrian Bridge construction contract, allowing fabrication to commence and on‑site installation to be scheduled for this spring.

20 May 2026
Major Projects
Myrtleford

The Nimmo Pedestrian Bridge will deliver a long‑requested pedestrian and cycling connection across the Ovens River in Myrtleford, improving safety and connectivity for residents and visitors.

The project was identified as a priority through community consultation following the 2019–20 bushfires and has been supported by funding from Emergency Management Victoria (EMV) and Council.

After Council awarded a design and construct contract to North East Civil Construction in March 2024, detailed investigations were undertaken to determine the safest and most suitable bridge location. A site downstream of the existing road bridge was selected to meet engineering requirements and avoid impacts on surrounding infrastructure.

During the detailed design phase, challenging ground conditions identified through geotechnical testing required a stronger and heavier bridge structure, including deeper piles and larger footings. Escalation in construction and material costs over the extended design period also contributed to an increase in the final project cost.

At its Ordinary Council Meeting in April, Council approved a variation to the contract to address these changes. EMV has also approved an extension to the funding agreement, with the final project milestone now set for November 2026.

Additional Council funding to cover the shortfall has been allocated from savings across Council’s existing Capital Works Program.

Alpine Shire Mayor, Cr Sarah Nicholas, said the decision ensures the project can proceed safely and responsibly.

“The Nimmo Pedestrian Bridge is an important investment in Myrtleford’s future, delivering a safer way for people to walk and cycle across the river,” she said.

“While the ground conditions presented unexpected challenges, Council has worked closely with engineers, funding partners and regulators to make sure the final design is robust, resilient and built to last.

“Approving this variation allows fabrication to begin and keeps this much‑anticipated project moving forward.

"We'd like to thank the Myrtleford community for their patience, and we look forward to delivering a key piece of infrastructure that supports safety, accessibility and active transport for years to come."

Fabrication of the bridge is now able to proceed, with installation planned for later this year.